Rehabilitation of Bahramtapa toBilesuvar Road(R42) (60 Km)

On the 01st of November 2018 GMC Consulting LLC signed an agreement with a Turkish consulting company BCT Insaat, Mimarlik, Muhendislik, Mushavirlik A.S. Company for Construction Supervision of Civil Works Contract for the Rehabilitation of (R42) Bahramtapa to Bilesuvar Road (60 Km).


Project description:

Under the Loan as the financial assistance provided by the European Bank for Reconstruction and Development (EBRD) for Construction Supervision of Civil Works Contract for the Rehabilitation of (R42) Bahramtapa to Bilesuvar Road (60 Km) the project aim was to rehabilitate the existing R42 road.

The works includes rehabilitation of 60 km Bahramtapa – Bilesuvar road section that starts at the roundabout on the M6 and ends at the junction at the end of the Bilesuvar western bypass. Reconstruction of the two lane single carriageway roads mainly follow the existing alignment includes earthworks, construction of pavement, drainage systems, replacement of three bridges and the installation of road furniture and road markings.

The Project Commencement date was the 07th of February 2019 and completed in October 2020.

The price of the Civil Works Contract was 140,831,783.00 AZN (82,842,225.29 USD).